Trees - how to safeguard them during construction work
Home > Services > Environment and Planning > Planning > Trees, Nature Conservation and Greenspace
The advice applies equally to developers of large sites and to residents extending their houses.
The information on this page is taken from the relevant British Standard (BS 5837:1991, 'Trees in relation to construction'). Further details are contained in the British Standard itself. To find out more or to obtain a copy of BS 5837:1991 visit the BSI website.
It is important to remember that all protective measures should be in place before any development work starts. Complete all protective works before bringing any machinery or vehicles onto the site or carrying out any demolition or soil stripping.
The need for protection
Such damage is frequently caused unwittingly, because of failure to appreciate the vulnerability of trees, particularly the root system, and how easily and often insidiously they can be damaged.
Irreparable damage is frequently done to existing trees and other planting in the first few days of a contractor's occupation of a site.
Damage to the trunk and branches of a tree rarely kills it, but may cause severe disfigurement.
Area to be enclosed by fencing
As large an area as possible should be enclosed by protective fencing. BS 5837 provides detailed guidance on the minimum area around the tree which should be left undisturbed (see section 7.5.4).
As a simple alternative, BS 5837 also suggests that fencing can be erected below the outermost limit of the branches spread, or at a distance equal to half the height of the tree, whichever is the further from the trees.
Specification of fencing
Protective fencing should be at least 1.2 metres high, comprising a vertical and horizontal framework of scaffolding, well braced to resist impacts, supporting either cleft chestnut pale fencing or chain link fencing.
Consultation with the planning service before removing fencing
The protective fencing is the most important consideration and it should not be removed before you consult the council's planning service. Take care at all times to avoid any equipment striking the trunk, branches or foliage.
Temporary removal of protective fencing
Where protective fencing has to be temporarily removed to allow construction work to be carried out, the fence should be removed and re-erected to the maximum distance possible from the trunk immediately before the works begin. The fence should then be re-erected in its original position immediately after the works have been completed.
Storage of materials and equipment
Oil, bitumen, cement and other materials likely to damage a tree should not be stacked or discharged within 10 metres of a trunk. Materials, including soil, should not be stacked or discharged within 5 metres of a trunk. Concrete mixing should not be carried out within 10 metres of a trunk. No site huts or machinery (including cement mixers) are to be stored within 10 metres of a trunk.
Roots
If excavations find root system greater than 25 metres in diameter, the council's planning service must be told immediately. Hand excavation should then be used to avoid damage. Roots requiring hand excavation should be surrounded with sharp sand before replacing with soil. Cement should not be placed in the vicinity of roots.
Stumps and fires
Stumps and felled trees should be removed by the contractor. Fires should not be lit in a position where the flames could extend to within 5 metres of foliage, branches or trunks.
For more information:
- email : pt@renfrewshire.gov.uk
- phone: 0141 842 5811/5822
- fax: 0141 842 5040
- call or write to:
Renfrewshire House
Cotton Street
Paisley
PA1 1LL
Back to top



